Jeakins Weir undertook the All Saints Church of England Primary School build project in three phases:

Enabling Works: The demolition of a number of minor buildings, construction of the main site set up and access route, including the use of heras fencing for 30 months. The design and construction of a new multi-use games area, including fencing.

Phase 1: Construction of a new hall split into two temporary classrooms, including WCs, Staff Room and a new Plant Room. Demolition of the existing Plant Room and the re-connection of the services.

Phase 2 : Construction of a new school, encompassing 14 new classrooms, offices, kitchen and associated accommodation, external works and the demolition of the existing school buildings.