The King’s School – Humanities Block

This was our second major project for King’s School. This 12 classroom new build was constructed in the school campus and next to the occupied school buildings. Access was very tight and we ensured deliveries were made out of school working hours so that they could be transported around the campus before of after the school working day.

Daily co-ordination with the school staff was required and we carefully planned out activities around the school working day. In particular, heavy and noisy works were carried out outside of school working hours and we also limited works during exam periods.

The work was completed on time and within budget. The completion of this building enabled the school to then carry out a major refurbishment and another extension of their existing school – a project which they also awarded to us.